Posted on: April 17, 2020

[ARCHIVED] Lane Reduction/Flagger Operation – US Highway 8


5/19/2020 UPDATE 

Project completion date has been extended through Wednesday, May 27, 2020. 


UPDATE: Project begin date has been postponed, due to weather.

Work will begin Thursday, April 30, 2020.

Price County Highway Department will begin crack sealing on US Highway 8 from County Highway O ending at the Rusk County Line.  The duration of the project is expected to last approximately 2 weeks.  US Highway 8 will be limited to one lane traffic from 7:30 a.m. to 3:30 p.m. within the work zone. Please allow extra time for you commute. Thank you.